While the concept is no mystery to those who participate in the construction industry. The means by which you protect these job related accounts receivables can be a little tricky.
Lets take a look at Texas.
Texas statutes actually require that the property owner hold 10% retainage from the total due the Original Contractor until the project has completed, and 30 days have elapsed. Why? Why does the State make this requirement upon the Property Owner? There may be several answers to this question. But the one that jumps out is: “To help defend against mechanics liens which those, other then the original contractor, are preparing to bring against the project due to unpaid contracts”.
By requiring the Property Owner to hold back (RETAIN) 10% of the amount due the Original Contractor for up to 30 days after the job is completed. Those with unpaid contracts can properly notice the property owner while funds are still available to satisfy these claims and protect the property owner from possibly paying twice for the materials, supplies or labor which was provided to the project under subcontracts.
Now the key to protecting all of your unpaid balances for this project is to have a crystal clear understanding as to what is retainage and what is not!
Key Takeaways
- Retainage Concept: Retainage is a portion of the contract payment withheld until the project is completed to protect the property owner from unpaid subcontractor claims.
- Compliance and Notices: To secure rights to retainage, it’s crucial to comply with all necessary notices and documentation requirements throughout the project duration.
- Lien Filing: If retainage and unpaid balances remain unresolved, filing a mechanics lien that includes both can secure payment, provided all conditions and deadlines are met.
Best way to explain is by illustration:
Lets say that you are the Plumbing Contractor for an improvement being made to Texas Corporate Park. You have subcontracted with the Original Contractor to install all of the plumbing fixtures for a total price of $650,000.00. You agree to a Retainage Agreement of 10%.
So from the very beginning of the project you know that $65,000.00 of the total due to you are not collectable until the TERMS of the RETAINAGE AGREEMENT has been satisfied. Lets also say that your work of this job will last 5 months and that you actually finish on time. To sweeten this illustration, you have 100% approval of your work by the Original Contractor and the Owner. I know, sounds like utopia. Bear with me for this illustration. Your contract of $650,000.00 should be paid in full. However, you agreed to allow 10% ($65,000.00) be subject to the retainage agreement. Your subcontract also most likely included terms for you to submit invoices as you completed select portions of your contract. Those invoices cannot total more than $585,000.00 and are due and payable to you during the course of the contract in accordance with your agreed terms.
To protect the $585,000.00 (amount of subcontract less retainage) you must submit all first and second notices of unpaid balances as they become due during the 5 month project, in order to secure your right to file a mechanics lien for unpaid balances. If you were 100% in compliance with the Texas notice of unpaid balances requirements, and unpaid balances which represent $75,000.00 of the $585,000.00 are owed to you. An affidavit of lien for $75,000.00 may be claimed. If your affidavit of lien is being claimed at a time which is also in agreement with the terms for retainage, and the retainage of $65,000.00 is also unpaid, you may file a single affidavit of lien for $140,000.00.
However, should the terms of the retainage agreement allow additional time for disbursement of the $65,000.00 you allowed to be withheld as retainage, you must limit your affidavit of lien to the $75,000.00 unpaid balances portion and consider an additional affivdait of lien for the retainage portion once the retainage agreement has matured and you have not been paid the $65,000.00 Retainage.
So the lessons to consider from this illustration are:
- Avoid mixing unpaid balances with retainage (Unless all amounts are due or past due)
- Make sure that you have complied with ALL Texas notices for retainage and unpaid balances. (Most will get the unpaid balance portion under control. It is the retainage protection which tends to get lost in the paperwork)
- Using a professional lien service, with years of experience with Texas notices, should greatly reduce the worry and keep all of your unpaid job related accounts receivable in compliance with the requirements that allow you to seek protection under the statutes.
Contact CRM for all of your notices in all 50 states.